Analisis Percepatan Waktu Dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off : Studi Kasus Proyek Pembangunan Prasarana Pengendali Banjir
DOI:
https://doi.org/10.18196/st.v19i1.2233Abstract
Time and cost have significanteffect on the success and failure of the projects.Thebenchmark for the success project is usually seen by short finishing time with the
minimum cost without leaving the quality.Project management systematically is
required to ensure the project implementation time in accordance with the contract
or even faster so the cost can provide benefits, and also avoid the penalty due to
delay in the completion of project. The aim of this research is to calculate the
changes of the cost and (overtime) and to compare the results between the cost of
penalty cost with the changes after adding the overtime.The secondary data
obtained from the contractor.Data analysis in this research is using Microsoft
Project 2007 program and methods of time cost trade off. The results of the
program Microsoft Project 2007 is the critical path and the results of the method of
time cost trade off is duration acceleration and cost increases due to the acceleration
of the duration in any activities that increased.The results of this study indicate that:
(1) From the time cost trade off with the addition of 1 hours of work per day
conducted on first day on critical jobs during the project, obtained the reduction in
the duration of 57 days, from the normal duration of 196 days to 139 days with a
total project cost changes from the normal cost of Rp 16,371,654,833.56 to Rp 16
133 .588.292,57 (the difference between the cost of Rp. 238,096,540.99) as well as
causing an increase in the direct cost of Rp 15,469,452,846.76 to Rp
15,493,731,373.36 (the difference between the cost of Rp. 24,278,526.60) and
indirect costs experienced a decrease of US $ 902,201,986.80 to Rp 639,826,919.21
(the difference between the cost of Rp. 262,375,067.59), (2) cost of accelerating the
duration of the project with overtime is cheaper than the cost to be incurred if
projects experienced delays and penalty.
Warning: file_put_contents(): Only 0 of 23 bytes written, possibly out of free disk space in /var/www/ojs-3.2.1-5/lib/pkp/classes/cache/FileCache.inc.php on line 90
Downloads
Published
2016-12-26
How to Cite
Priyo, M., & Sumanto, A. (2016). Analisis Percepatan Waktu Dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off : Studi Kasus Proyek Pembangunan Prasarana Pengendali Banjir. Semesta Teknika, 19(1), 1–15. https://doi.org/10.18196/st.v19i1.2233
Issue
Section
Articles
License
Semesta Teknika is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).