Studi Optimasi Waktu dan Biaya dengan Metode Time Cost Trade Off pada Proyek Konstruksi : Studi Kasus Proyek Jalan Bugel-Galur-Poncosari Cs. Tahap I, Provinsi D.I. Yogyakarta

Mandiyo Priyo, Sarwidi Sudiro

Abstract


The important things that neededto know when planning the construction project are to optimize the time and the cost. To set the good time and the good cost for the implementation will give benefit greatly or maximum and avoid the cost of penalties for project delays. It is necessary to optimize the time and cost with creating the networking, searching for critical activities, and also calculate the duration of the project implementation and a number of resources. The purposes of this research are to know the changes in cost and time of the project implementation with a variety of additional work hours, employers, and equipments, to know the changes in time and cost of the project implementation with the additional variety of equipments and employee, and to know the comparison between the penalty cost and the additional of work hours cost, the additional of equipment cost, and also the additional of employs. The data used in this study is from the road construction project data of Bugel-GalurPoncosari Cs (Stage I). The data analysis of this research uses Microsoft Project 2010 and the method is time cost trade off. The critical path and the cost increase due to work hours additional obtain from the computer analysis of Microsoft project 2010, also the acceleration duration and cost increases due to the duration acceleration of the results obtains from the analysis method of time cost trade off. The results of this study are (1) the time and cost of the project in normal conditions with duration of 177 days and a cost of Rp 40,897,811,578.00, additional 1 hour of additional work hours obtains from crashing duration of 110.03 days, the cost is Rp 40,076,775,588.21. The addition of 2 hours additional work hours obtains from crashing duration of 62.1 days, the cost is Rp 39,633,316,095.13. The addition of 3 hours additional work hours obtains from crashing duration of 26.89 days, the cost is Rp 39,369,085,607.83. (2) The addition of equipment and employers using a duration of 1 hour additional work hours with a duration of crashing of 110.03 days, the cost is Rp 39,931,863,398.85. The addition of equipment and employers with duration of 2 hours additional work hours crashing duration of 62.1 days, the cost is Rp39,240,658,440.70. The addition of equipment and employers with duration of 3 hours additional work hours crashing duration of 26.89 days, the cost is Rp 38,733,785,415.45. (3) To accelerate the duration of the project cost with the addition of equipment and employers is efficient and cheap when compared to the addition of work hours, and also cheaper than the costs incurred if the project has been delayed and subject fined. 


Keywords


Time Cost Trade off, Microsoft Project 2010, Additional of Work Hours, Additional of Equipments, Cost, Time

Full Text:

PDF

References


Dwijono, D., 2017,Optimalisasi Waktu Percepatan dan Biaya Kegiatan di dalam Metode Jalur Kritis dengan Pemrograman Linier, Jurnal Terapan Teknologi Informatika, 1(1), pp. 1-9.

Dipohusodo, I., 1996,Manajemen Proyek Dan Konstruksi,Yogyakarta: Kanisius.

Frederika, A., 2010,Analisis Percepatan Pelaksanaan dengan Menambah Jam Kerja Optimum pada Proyek Konstruksi (Studi Kasus Proyek Pembangunan Super Villa Peti TengetBadung, Jurnal Ilmiah Teknik Sipil, 14(2), pp. 113-126.

Ikhtisholiyah, 2017,Analisis Penerapan Manajemen Waktu dan Biaya pada Proyek Pembangunan Gedung Kuliah Teknik Listrik Industri Politeknik Negeri Madura (POLTERA),Zeta - Math Journal, 3(1), pp. 14-21.

Kareth, M., 2012,Analisis Optimalisasi Waktu dan Biaya Dengan Program Primavera 6.0 (Studi Kasus Proyek Pembangunan Puri Kelapa Gading), Jurnal Sipil Statik, 1(1), pp. 53-59.

Khodijah, N.S., Yahdin, S., Dewi, N.R., 2013,Optimalisasi Pelaksanaan Proyek Pembangunan Persinyalan Elektrik di Stasiun Kertapati dengan Penerapan Metode Crash Program, Jurnal Penelitian Sains, 16(2A), pp. 65-74.

Pawiro, D.A., Suharyanto, Atmojo, P.S., 2014,Optimalisasi Biaya dan Waktu dalam Penyusunan Jadwal Pelaksanaan Proyek (Studi Kasus Proyek Pembangunan Gedung Pusat Kegiatan Mahasiswa Universitas Diponegoro Semarang,. JurnalMedia Komunikasi Teknik Sipil, 20(2), pp. 103-108.

Priyo, M., Sumanto, A., 2016,Analisis Percepatan Waktu dan Biaya Proyek Konstruksi dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off (Studi Kasus Pembangunan Prasarana Pengendalian Banjir), Jurnal Ilmiah Semesta Teknika, 19(1), pp. 1-15.

Simatupang,J.S., 2015,Pengaruh Percepatan Durasi Terhadap Waktu Pada Proyek Konstruksi (Studi Kasus Pembangunan Persekolahan Eben Haezar Manado), Jurnal Sipil Statik, 3(5), pp. 281-291.

Soeharto, I., 1995,Manajemen Proyek Dari Konseptual Sampai Operasional,Jakarta: Erlangga.

Telaumbanua,T.A., 2017,Perencanaan Waktu Penyelesaian Proyek Toko Modisland Manado dengan Metode CPM, Jurnal Sipil Statik, 5(8), pp. 549-557.

Wowor,F., 2013,Aplikasi Microsoft Project dalam Pengendalian Waktu Pelaksanaan Pekerjaan Proyek, Jurnal Sipil Statik, 1(8), pp. 543-548




DOI: https://doi.org/10.18196/st.v20i2.3410

Refbacks

  • There are currently no refbacks.


Copyright (c) 2017 Jurnal Semesta Teknika

Editorial Office :

SEMESTA TEKNIKA

Faculty of Engineering, Universitas Muhammadiyah Yogyakarta.

Jln. Brawijaya Tamantirto Kasihan Bantul 55183 Indonesia

Telp:(62)274-387656, Fax.:(62)274-387656

Email: semesta_teknika@umy.ac.id, semestateknika@umy.university

Website: http://http://journal.umy.ac.id/index.php/st

Creative Commons License

Semesta Teknika is licensed under a Creative Commons Attribution 4.0 International License.